ProjectsADNOC Petrol Stations
ADNOC Petrol Stations
Civil Works
/05

ADNOC Petrol Stations

Northern Emirates · ADNOC Distribution

Size
8,000 m²
Completed
2023
Duration
18 months

Multi-site civil works across ADNOC petrol stations in the Northern Emirates. The scope included concrete works, block work, plastering, MEP infrastructure, and forecourt surfacing.

Project Scope
  • Concrete foundations and slab works
  • Block work and masonry construction
  • Plastering and finishing
  • MEP infrastructure coordination
  • Forecourt surfacing and canopy works
Key Highlights

Delivered 6 station sites simultaneously

Met ADNOC's strict safety and quality benchmarks

Zero lost-time incidents across 18-month programme

Execution Timeline
Site Prep
Week 1-6
Clearance, excavation, utility mapping
Foundation
Week 7-16
Concrete works, block work, structural elements
MEP & Services
Week 17-30
Underground services, tank installation, MEP
Surfacing & Canopy
Week 31-52
Forecourt surfacing, canopy structure, signage
Testing & Commissioning
Week 53-72
Fuel system testing, safety inspection, handover
Features
Concrete WorksBlock WorkPlasteringMEP InfrastructureSafety Compliance
Project value
AED 12M
Request a consultation

Our technical team replies within 24 hours. No commitment required.