Large-scale ACP cladding, aluminium and glass works for a contemporary retail mall in Dubai. The project involved facade installation, curtain wall systems, and premium glazing across multiple retail floors.
Project Scope
- ACP cladding installation across full facade
- Aluminium curtain wall systems
- Structural glazing and glass facade
- Aluminium fabrication for retail units
- Weatherproofing and sealant works
Key Highlights
Installed 4,500 sqm of ACP cladding with zero panel defects
Coordinated aluminium works with MEP facade penetrations
Completed ahead of mall opening schedule
Execution Timeline
Fabrication
Week 1-8
Panel fabrication, aluminium cutting, glass tempering
Structural
Week 9-20
Substructure, brackets, anchoring systems
Installation
Week 21-40
ACP panels, curtain wall, glazing
Finishing
Week 41-52
Sealant, testing, cleaning, handover
Features
ACP CladdingCurtain WallStructural GlazingAluminium Fabrication
Project value
AED 8.1M