Sharjah Villa — Full Interior Renovation

Villa Renovation — Sharjah & Nadd Al Hamar

Sharjah & Nadd Al Hamar, Dubai · Multiple Private Clients

Size
400 - 1,200 m²
Completed
2022-2025
Duration
Varies

Multiple villa renovation projects across Sharjah and Nadd Al Hamar, ranging from full structural modifications to interior fit-outs. Each project tailored to client requirements with premium finishing.

Project Scope
  • Structural modifications and extensions
  • MEP upgrades and AC replacement
  • Flooring, tiling, and marble works
  • Kitchen and bathroom renovations
  • Exterior painting and landscape updates
Key Highlights

Completed 12 villa renovations across 3 years

100% client satisfaction rate on all delivered projects

Average project duration reduced by 20% through process optimization

Execution Timeline
Consultation
Week 1-2
Client meeting, design discussion, budget alignment
Design & Approval
Week 3-4
Drawings, authority approvals, material selection
Demolition & Prep
Week 5-6
Strip-out, structural prep, site protection
Construction
Week 7-16
Structure, MEP, tiling, joinery, painting
Finishing & Handover
Week 17-20
Final touches, cleaning, client walkthrough
Features
Structural ModificationMEP UpgradePremium FinishingCustom Design
Project value
AED 1.2M - 3.5M
Request a consultation